Close & hand over

Close & Hand Over: From Signed Term Sheet to Financial Close and Smooth Transition

We convert negotiated terms into binding, bankable agreements and drive the deal to financial close — coordinating due diligence, finalising definitive agreements, tracking conditions precedent, and managing the operational handover so the authority, the concessionaire and lenders start the concession period with no loose ends.

Typical duration · 10-16 weeks from term sheet to financial close, plus 4-8 weeks transition support

Samples generated 07 Sept 2026, 07:55 am IST

What happens in this step

  1. 01Coordinate legal, technical, financial and environmental due diligence across advisors, resolving red-flag items before they threaten timelines
  2. 02Finalise definitive agreements — concession/PPP agreement, state support agreement, escrow and substitution agreements, O&M and EPC contracts — aligned to the negotiated term sheet
  3. 03Build and track a conditions-precedent (CP) matrix across authority, concessionaire and lender obligations, with a single-point tracker and weekly status calls
  4. 04Support lender due diligence, credit committee queries and facility agreement finalisation for financial close (debt and equity draw-down)
  5. 05Coordinate signing logistics, notarisation, stamping/registration and regulatory filings (competition/FDI/sectoral approvals as applicable)
  6. 06Manage the transition plan — asset handover protocols, employee transfer, data room closure, baseline condition surveys, and performance-security lodgement
  7. 07Set up post-close governance — monitoring dashboards, reporting calendars, dispute-resolution triggers, and first-90-day obligation tracking
Footage

Close & hand over · on the ground

Video · RDNE Stock project / Pexels

What we need from you

  • Agreed term sheet / letter of award and negotiated risk allocation
  • Draft definitive agreements and prior due-diligence reports (legal, technical, environmental)
  • Lender information memorandum and financing term sheet
  • List of conditions precedent from all parties (authority, concessionaire, lenders)
  • Asset registers, employee rolls and existing contracts for transition planning
  • Insurance, performance security and guarantee formats required under the concession
  • Statutory approval status (environmental clearance, land title, regulatory consents)
Overhead view of professionals discussing financial graphs and using calculators in an office setting.
Image

Your inputs, our engineering

Photo · Vlada Karpovich / Pexels

Worked example (anonymised, illustrative)

300-Bed Multi-Specialty Hospital PPP (DBFOT) · 300 beds, tertiary care, 22-year concession · Eastern India

State health department awarded a DBFOT hospital concession; advisory led financial close coordination across 14 CPs, definitive agreement finalisation, and a 10-week handover of the partially built asset to the concessionaire's O&M team.

What you receive

Sample deliverables from this step

Every sample below is analyst-written and anonymised for illustration — structure and depth mirror our real deliverables; figures and names are not from any client engagement.

Illustrative — Conditions Precedent (CP) TrackerIllustrative · Growthifye-prepared
schedule

Conditions Precedent (CP) Tracker

Master matrix of all CPs across authority, concessionaire and lenders, with owners, evidence required and closure status.

Sample excerpt · CP tracker excerpt (14 of 41 items) — illustrative figures

#CP itemResponsible partyStatusTarget date
3Land handover certificate (12.4 acres)State health deptClosedWk 4
7Environmental clearance (EC) amendmentConcessionaireIn progressWk 6
11Escrow account opening & waterfall set-upLender/ConcessionaireClosedWk 5
18Performance security (INR 18 cr) lodgementConcessionaireIn progressWk 8
24Insurance policies (CAR + third-party)ConcessionairePendingWk 9
31Lender legal opinion & CP certificateLenders' counselPendingWk 10
38State guarantee / support undertakingState govtClosedWk 7
  • Weekly CP call with authority, lenders and concessionaire until closure
  • Financial close conditional on all lender CPs being satisfied or waived
Download illustrative sample (PDF)
Illustrative — Definitive Agreements PackageIllustrative · Growthifye-prepared
memo

Definitive Agreements Package

Finalised concession agreement, state support agreement and O&M contract, redlined against the negotiated term sheet with a change log.

Sample excerpt · Definitive agreement change log (sample clauses) — illustrative figures

ClauseTerm sheet positionFinal agreementRationale
Change in scope cap10% of capex12% of capexLender requirement for buffer
Termination payment (authority default)100% debt + 90% equity100% debt + 80% equityNegotiated risk-sharing
O&M performance securityINR 5 crINR 6 crAligned to O&M contract value
Handback condition standardAs-isResidual life >75%Authority protection clause
Force majeure cap180 days270 daysPost-COVID market practice
  • All redlines tracked against board-approved term sheet
  • Final versions circulated for signature only after lender no-objection
Download illustrative sample (PDF)
schedule

Handover & Transition Plan

Day-wise transition plan covering asset baseline surveys, employee transfer, data room closure and first-90-day operational obligations post financial close.

Sample excerpt · Transition milestones (illustrative, Weeks 1-10) — illustrative figures

WeekMilestoneOwnerDeliverable
1-2Baseline condition survey of built structureIndependent engineerBaseline report + photo log
3-4Employee transfer / contract novationAuthority + ConcessionaireTransfer list signed
5-6Equipment & inventory handoverO&M contractorAsset register reconciliation
7-8Performance security & insurance in placeConcessionaireCompliance certificate
9-10Data room closure & final completion certificateAdvisory + AuthorityClosure memo
  • Independent engineer certifies baseline condition to prevent future handback disputes
  • Same transition framework used for toll-road TOT bundles and power asset transfers, adjusted for asset-specific baseline surveys
Download illustrative sample (PDF)
dashboard

Financial Close Report & Post-Close Governance Dashboard

Consolidated financial close certificate with funding flow confirmation, plus a live dashboard for post-close monitoring of milestones, reporting obligations and dispute triggers.

Sample excerpt · Post-close monitoring dashboard (sample fields) — illustrative figures

MetricFrequencyThresholdCurrent status
Construction progress vs scheduleMonthly±5% of planOn track
Debt service reserve balanceQuarterlyMin. 1x DSCRCompliant
O&M KPI compliance (uptime, response time)Monthly≥98% uptime97.6% - flagged
Insurance renewal statusAnnualNo lapseRenewed
Regulatory filing complianceQuarterly100%Compliant
  • Dashboard shared with authority, lenders and concessionaire for transparency
  • Early-warning flags trigger a defined escalation protocol before formal default notices
Download illustrative sample (PDF)

Outcomes

  • Financial close achieved on schedule with all CPs satisfied or formally waived by lenders
  • Definitive agreements legally binding and consistent with negotiated commercial terms, minimising future disputes
  • Clean, documented asset and operational handover reducing early-stage disputes and handback risk
  • Post-close governance framework in place from day one, giving authority and lenders real-time visibility on obligations
Footage

Outcomes that reach COD

Video · invisiblepower / Pexels

Questions clients ask

What happens if a condition precedent cannot be met by financial close?

We work with counsel to structure a formal waiver or conditional close mechanism, agreed by lenders, with a backstop date and remedy plan — common for items like pending sub-approvals that don't threaten project viability.

Does this step apply the same way to energy assets like transmission lines or renewable IPPs?

Yes — the CP tracker, definitive agreement finalisation and financial close process are near-identical for a transmission BOOT project or a solar-plus-storage IPP; the main variation is technical CPs such as grid connectivity approval or fuel/PPA conditions replacing land or clinical-service conditions.

Who leads coordination between the authority, concessionaire and lenders during this phase?

Our team acts as the coordinating secretariat, running the CP tracker and weekly calls, while legal counsel and lenders' engineers retain sign-off authority on their respective workstreams.

A diverse group of professionals in a business consulting office setting.
Image

Questions we answer every week

Photo · Tran Nhu Tuan / Pexels

We use essential cookies to run the site and, with your consent, track your activity to personalise your learning and recommendations. See our Privacy Policy.