RE Advisory · Regulatory navigator · 36 states & UTs · links re-checked weekly

Every approval, every state — from single window to COD

Click a state for its single-window portal, STU / CTU connectivity, CEIG drawing approval & inspection, fire NOC, permission to charge (Format I & II), commissioning & COD and PM-KUSUM — each step marked online or manual with the procedure, documents and official links. Blue dots are STU substations with capacity available for injection (as-on date shown).

Shade = share of steps filed online · 0 substations plotted · links checked 8/9/2026

DL · 2 manual · 6 online

Delhi

Generation & grid map

Single window

Delhi single window (DIDC)

industries.delhi.gov.in !

Nodal RE agency

EE&REM Centre / IPGCL

ipgcl-ppcl.gov.in !

STU (transmission)

Delhi Transco

dtl.gov.in

Electrical Inspectorate (CEIG)

Electrical Inspector, Delhi

manual filing (no portal — manual)

Fire services

Delhi Fire Service

dfs.delhi.gov.in !

Regulator / DISCOM

DERC

Approval chain · click a step for procedure, documents & timeline

Authority: Delhi single window (DIDC) · industries.delhi.gov.in !

  1. 1.Register the SPV / project on Delhi single window (DIDC) (CAF — Common Application Form) and select RE power generation as the activity.
  2. 2.Nodal agency EE&REM Centre / IPGCL registers the project (registration / facilitation fee as per state RE policy) — carry the registration letter into every downstream application.
  3. 3.Apply for land conversion (NA / industrial use), stamp-duty concessions and electricity-duty exemptions under the state RE policy through the same CAF.
  4. 4.Track application status and deemed-approval timelines published on the portal; escalate through the grievance module if SLAs lapse.

Documents

  • · SPV incorporation documents & PAN/GST
  • · Land ownership / lease title, 7/12 or khasra extracts
  • · Project DPR & layout
  • · Board resolution and authorised signatory ID

Indicative timeline

15–45 working days (state SLA; deemed approvals in most states)

Technology-specific approvals · generation × transmission × distribution

generation

  • ALMM / DCR compliance declaration for modules & cells (MNRE) where the PPA or scheme requires it national
  • Environment: solar is exempt from EIA notification; obtain Consent to Establish / Operate (CTE/CTO) from the State Pollution Control Board only where the state insists (e.g. large floating solar on reservoirs) state
  • Floating solar — water-body lease / NOC from the irrigation or water-resources department and the dam-safety authority state

transmission

  • Right-of-way for the dedicated line under Sec. 164 (Telegraph Act powers) — state notification + compensation per MoP RoW guidelines 2024 state
  • Railway / NH / river / canal crossing approvals and PTCC clearance (Power Telecom Coordination Committee) for lines ≥ 33 kV national

distribution

  • Net / gross metering or feeder-level agreement with the DISCOM for ≤ 5 MW distributed plants (state net-metering regulations) state
Substations with capacity available for injection · Delhi Transco

As on 2020-03-04 · checked 8/9/2026

Not yet pulled — the weekly job scans the STU website for the latest 'available capacity' publication.

Procedures summarised from CEA / CERC regulations and state RE policies; portal links point to official government domains and are re-checked weekly. Where a step is marked MANUAL the state has no online filing — the procedure describes the physical process. Verify current timelines with the nodal agency.